Vanta Logistics
Rebuilding dispatch for 6.2 million parcels a day
Vanta Logistics lost four hours of dispatch during peak week 2022 and 340,000 parcels missed their promised day. We rebuilt the scheduler as an event-driven service that has since carried 6.2 million parcels on its busiest day without a dispatch outage.
- Client
- Vanta Logistics
- Sector
- Logistics
- Run
- 14 months · Mar 2023 – Apr 2024
- Filed
- 2024-06-03
- Capability
- Platform modernisation · Systems integration · Reliability engineering
- Stack
- Go · Apache Kafka · PostgreSQL 16 · gRPC · Redis · Kubernetes · Google Cloud · Terraform · Grafana

Impact
99.98%
Dispatch availability in peak week, up from 97.1%
40 s
Reroute after a depot outage, down from 17 minutes
6.2M
Parcels routed on the busiest single day
Challenge
Logistics
14 months · Mar 2023 – Apr 2024
The scheduler was a single-writer monolith against one Oracle instance: it could not be scaled out, and it could not be tested, because no environment other than production had realistic parcel volume. A deploy took ninety minutes and a rollback took longer, so the team froze changes for the eight weeks around peak — which meant every fix found in October waited until January. When the scheduler stalled on 12 December 2022 it took nineteen minutes to notice and three and a half hours to recover, because recovery meant replaying a batch nobody had replayed before.
Solution
We extracted routing, capacity and depot assignment into separate Go services communicating over Kafka, so a depot outage now reroutes rather than blocks. Before any of it went live it ran in shadow against a mirrored copy of production traffic for eleven weeks, and we compared its routing decisions against the monolith’s parcel by parcel until the divergences were explainable. Failure was rehearsed rather than assumed: monthly game days kill a depot, a broker and a database primary in turn, and recovery runbooks are the artefacts those exercises produce. Deploys went from ninety minutes to six, which removed the argument for the peak-season freeze — the team now ships around forty times a week, including through December.
Plates

Plate 01One monolith became three services with independent failure domains. 
Plate 02Eleven weeks of shadow traffic before a single real parcel moved. 
Plate 03Recovery times come from rehearsals, not from estimates.
Testimony
Our dispatch system had one test when they arrived. Arcwright wrote 1,400 more before they changed a single line of it. Six months later a release takes twenty minutes instead of nine hours, and nobody stays late for it.
Petra Lindqvist · VP Engineering, Vanta Logistics5 out of 5